The direction of the overlap is opposite to the direction of the prevailing winds.
Onduline roofing sheets overlap.
Onduline roofing only comes in one length 2m x 0 95m so your first port of call should be to ensure that you have enough material for the job.
Ensure watertightness at ridge by applying the onduvilla foam fillers on both sides of the ridge line.
Overlap and side overlap.
Overlap 12 cm 3.
The ridge element should overlap the onduline sheet at minimum 14 cm.
Start fixing sheets at the opposite to prevailing winds end of the roof.
Of course sheets can be cut but there s a minimum requirement for overhang 70mm at the eaves and pitching 5 degrees.
Slope of the roof.
Ensure waterproofing by aligning the overlapping lines.
To have a long lasting and guaranteed roof it is mandatory to follow the nailing order and pattern ridges start fixing the ridge element opposite to the prevailing winds end of the roof.
15 fixings minimum should be used per sheet.
Lay ridge elements with a minimum overlap of 12 5 cm.
Get your measurements right.
Cover the ridge with the slim cap and fix it on each side of the roof through the foam fillers on top of the corrugations.
The roof slop is often stated as the inches of vertical rise per 12 inches of horizontal run length.
The rise if the vertical distance of the ridge above the eave.
Up signs indicate the direction of the ridge to lay the sheets correctly.
The slope of the roof can be calculated from measurements of the rise and run of the roof.
Fix 19 nails or screws per sheet to have a longlasting and guaranteed roof.
Begin every second raw with a sheet cut in half vertically.